In summary The Oaks, Coventry

A high-profile development of purpose-built student accommodation next to Warwick Universities’ 750-acre main campus on the outskirts of Coventry. The private student residences ranged from 4-7 storeys and were completed using our bespoke light steel framing system. The project at Westwood Way represented Phase 2 of the overall scheme and consisted of four separate buildings containing a total of 625 beds.

Project Introduction Construction details Application Details Download Full Case Study
Return to all Case Studies

A series of low-rise office buildings constructed in the 1970’s had to be demolished and the area cleared before construction commenced. The light steel installation kicked off in September 2020 and completed in June of the following year.

This meant the finished version of the building could be handed over to the University team in time for the new influx of students in September.

At a Glance

By working closely with the main contractor and understanding some of the logistical challenges onsite, we were able to identify some solutions to help address this.

We manufactured, delivered and assembled large HRS beams and columns weighing circa 3 tonnes in order to erect a link bridge to assist with access between Block C and B. The steels were coated in a bespoke 80 microns coating which left a superb finish – visually attractive as well as hugely practical.