In summary Streatham Regeneration, London

The site of the former Streatham Ice Rink has been re-developed to create a new supermarket with a 6 storey residential building on top using light steel framing.

Project Introduction Construction details Gallery Application Details
Return to all Case Studies

Light steel framing is the preferred solution where weight saving and speed of construction are fundamental to the success of the project.

The re-development of the former Streatham Ice Rink site was made economically feasible by building a 3 to 6 storey residential building over a major new Tesco supermarket, and by relocating the new ice rink and bus station to either side. The £80 million project provides 250 apartments arranged in a courtyard form.

Metek was chosen by the main contractor, for this project because of their joint experience on similar projects.

The residential building is supported by long span composite beams at the podium level. The building is in 5 distinct parts, of which three are for private housing, and two are for a mixture of shared ownership social rented and key workers.

The split of apartment sizes is: 166 two bedroom apartments of approximately 85m² floor area, 90 single bedroom apartments of 55m² floor area and 6 three bedroom apartments of 115m² floor area.

The construction of Metek’s light steel framing started in October 2012 and finished in April 2013. Importantly, deliveries to the site on the busy Streatham High Street were kept to the minimum and one lorry could provide sufficient wall panels for 2 days work. Highly accurate installation and absence of waste and site noise were other benefits of light steel framing.

The light steel structure supports a composite floor slab of 170mm depth that spanned up to 5m between the cross-walls. A composite slab was chosen for its excellent acoustic and stiffness properties. Despite the weight of the concrete, the total weight of the construction system was only 60% of that of a concrete flat slab.

The total floor area of the residential building was close to 19,000m², and its estimated total cost was £30 million of which the light steel framing part was only 12%. Light steel framing was also used for the penthouses at roof level, and the roof was supported by C-section purlins. The cladding was insulated render attached to cement particle board that was directly screw fixed to the light steel external walls. A U-value of 0.2 W/m²K was achieved.

The apartments also included 3m wide and 1.5m deep steel balconies that were attached to steel posts through thermal ‘breaks’. Metek designed and installed the hot-rolled steel balconies and also installed the decking, reinforcement, external boarding and the pre-cast concrete stairs as part of their ‘package’ with the main contractor.