In summary Project Atria, Cambridge

A World-class medical research centre in Cambridge.

Or bespoke LGSF package for this World-class research centre in Cambridge, was designed to achieve a high level of prefabrication and quality control for this complex building.

Project Introduction Construction details Gallery Application Details Testimonials Download Full Case Study
Return to all Case Studies

We were specifically engaged by the main contractor SDC because of our ability to pre-fabricate as much of the light steel infill walls and associated steelwork as possible, in order to minimise personnel on site and to speed up the overall construction process. The double height infill walls between the 1st to 3rd floor were manufactured offsite at our Wolverhampton factory and were installed as large panels of 8.2m height and up to 2.4m width. The panels were pre-boarded to provide a weather-tight envelope to which the cladding rails were later attached. The curved façades at the corners of the building were constructed using facetted narrow infill walls to create the curved appearance.

Project Delivery

The 450mm, deep post-tensioned concrete slab and concrete frame were constructed first and we had to carry out a site survey of finished slab levels in order to be able to fit in the large infill wall panels, with the required 20mm provision for long term movement with only 5mm tolerance. The over-sail infill walls were connected to the 2nd floor slab by 4mm thick galvanized U sections bolted to horizontal cast-in channels in the slab The single storey high walls at ground floor were a more conventional ‘stick built’ infill wall.

We were also engaged to provide a ‘package’ of steel components, including the Rectangular Hollow Section posts and curved steelwork and infills at parapet level, and the two 8m high tubular steel flue towers at roof level. These structures were pre-fabricated and installed with their cladding and flues attached and anchored to the slab upstands by 4 holding down bolts at each tubular column. Finally, we also responsible for the manufacture and installation of the infill walls to the roof-top plant rooms.

Challenges & Solutions

This project posed many manufacturing, logistical and constructional challenges but was completed on time and on budget leading to provision of a new much-needed high class medical facility to meet the challenges of this and future pandemics. It was refreshing working with the main contractor, SDC, who have fully embraced LGSF and all its benefits and we look forward to working with them on similar projects using the same manufacturing and installation system, which were heralded as a huge success on this scheme.