In summary Forge Island, Rotherham

Metek were appointed by Bowmer + Kirkland to deliver the structural frame for a new 69-room Travelodge hotel. The hotel is the first occupier to open at Forge Island – a once-derelict site now transformed into a family-friendly destination.

Project Introduction Construction details Gallery Application Details Testimonials Download Full Case Study
Return to all Case Studies

Working with Bowmer + Kirkland once again, the Travelodge project featured SFS infill to the cinema, restaurant, café, and hotel areas above a reinforced concrete ground floor podium.

Metek provided an end-to-end solution including three storeys of LGSF, bespoke SFS infill panels, concrete floors, and a joisted roof — delivering approximately 2,300m² GIFA.

The scope was increased during the build to include a galvanised HRS plant screen perimeter, designed, manufactured, and installed within three weeks.

Metek’s integrated approach ensured cost and programme certainty, with close coordination alongside the main contractor. The comprehensive delivery, from LGSF to plant screen structures, reflected a trusted relationship built over multiple projects.